CRITICAL SUPPLY CHAIN INEFFICIENCIES IN PAKISTAN’S CONSTRUCTION INDUSTRY: EMPIRICAL EVIDENCE FROM INDUSTRY PROFESSIONALS

Authors

  • Dr. M. Adil Khan
  • Hamza Farooq
  • Abdul Wahab
  • Kashif Daud

Keywords:

Construction supply chain, project delays, cost overruns, contractual disputes, procurement inefficiencies, stakeholder coordination, Pakistan construction industry

Abstract

The construction industry in Pakistan continues to experience persistent project delays, cost overruns, and stakeholder disputes, largely driven by inefficiencies within supply chain management practices. Despite the sector’s economic importance, empirical evidence systematically identifying the nature and severity of these inefficiencies remains limited. This study investigates the critical supply chain challenges affecting construction project performance in Pakistan using a quantitative, cross-sectional research design. Data were collected through a structured questionnaire administered to 108 construction professionals, including project managers, contractors, engineers, and supply chain specialists. Descriptive statistical techniques, frequency analysis, and one-sample t-tests were employed to examine operational, financial, governance, and coordination-related inefficiencies within the construction supply chain.

The results reveal statistically significant evidence of widespread supply chain inefficiencies across all examined dimensions. Inefficient procurement processes, delayed payments, and weak contract management emerged as the most prominent contributors to cost overruns, while fragmented communication among stakeholders was identified as a major source of resource mismanagement. Governance-related challenges, particularly limited transparency and trust in financial transactions, were found to contribute substantially to dispute occurrence. Furthermore, the findings indicate that a considerable proportion of construction projects experience moderate to high schedule overruns, frequently exceeding 50% of planned timelines due to supply chain disruptions. Reliability analysis confirmed strong internal consistency of the measurement instrument, supporting the robustness of the empirical results.

This study contributes to the construction management literature by providing practitioner-based empirical evidence of systemic supply chain inefficiencies in a developing economy context. The findings offer practical insights for industry stakeholders and policymakers, emphasizing the need for improved procurement practices, strengthened contractual frameworks, and enhanced coordination mechanisms. The study also establishes a foundation for future research and digital transformation initiatives aimed at improving construction supply chain performance in Pakistan.